Categories
Archive
Client |
Project Name |
Project Description (Details of Works) |
DYNA MAC | Shell Malampaya Topside Phase 3 | Various fields in piping system, mechanical & equipment installation and commissioning, blasting & painting & pre-commissioning works. |
KBS | Bras Sete 2 Semi-Submersible Rig | Piping Works for Pontoon & Lower Column Part & STBD of M-962 Bras Sete 2 (H-103) |
FBM Hudson Italiana | Hydrojetting, Chemical Cleaning, Air/Vacuum Drying & Nitrogen Blanketing | Hydrojetting, Chemical Cleaning, Air/Vacuum Drying & Nitrogen Blanketing |
Toyo-Thai Corporation Public Co. Ltd. | Chemical Cleaning Work | Precommissioning Works for JG Summit Petrochemical Corporation Capacity Expansion Project |
DAELIM |
JG Summit Naphtha Cracker Project |
Chemical Cleaning and Welding Work. Mobilization - including moving in of equipment from yard to project site and personnel. Demobilization - including moving out of equipment from project site to yard. Service and support for project, indirect manpower and consumables. |